Violation Detail
Standard Cited: 19100038 F03 Emergency action plans.
Inspection Nr: 993165.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $5,000.00
Current Penalty: $5,000.00
Issuance Date: 02/03/2015
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 03/02/2015
Gravity:
Report ID: 0214700
Contest Date: 02/24/2015
Final Order: 07/06/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/06/2015 | $5,000.00 | 03/02/2015 | Other | |
Penalty | C: Contested | 02/26/2015 | $5,000.00 | 03/02/2015 | Serious | |
Penalty | Z: Issued | 02/03/2015 | $5,000.00 | 03/02/2015 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.38(f)(3): The employer did not review the emergency action when the plan was changed: a) At the worksite, Employees were exposed to an emergency action plan that was not amended due to on going construction; on or about 9/2/14. Note: In addition to abatement certification, the employer is required to submit abatement documentation for this item in accordance with 29 CFR 1903.19.