Violation Detail
Standard Cited: 19100179 N03 III Overhead and gantry cranes.
Inspection Nr: 959735.015
Citation: 01001
Citation Type: Other
Abatement Date: 07/18/2014 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 06/19/2014
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity:
Report ID: 0636900
Contest Date: 07/09/2014
Final Order: 03/30/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/30/2015 | $7,000.00 | 07/18/2014 | Other | |
Penalty | C: Contested | 07/17/2014 | $7,000.00 | 07/18/2014 | Serious | |
Penalty | Z: Issued | 06/19/2014 | $7,000.00 | 07/18/2014 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.179(n)(3)(iii): During hoisting care was not taken to ensure sudden acceleration or deceleration of the load or at that the load did not contact any obstructions. On or about February 26, 2014, and times prior thereto, LP Branden Winches not approved for the hoisting of personnel were used to hoist employees performing maintenance.