Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 92578.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $7,000.00
Current Penalty: $0.00
Issuance Date: 12/27/2011
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0524530
Contest Date: 01/18/2012
Final Order: 04/22/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/25/2013 | $0.00 | Serious | ||
Penalty | C: Contested | 03/08/2012 | $7,000.00 | Serious | ||
Penalty | Z: Issued | 12/27/2011 | $7,000.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.119(d)(3)(ii): Equipment did not comply with recognized and generally accepted good engineering practices: (a) In the DU1 unit at the P-3683 suction pump, the one inch three-hundred pound seal flush auxiliary piping line was made up with threaded connections and improperly fabricated pipe nipples. The configuration subrogated fabrication specifications as prescribed in American Petroleum Institute Standard 610, Centrifugal Pumps for Petroleum, Petrochemical and Natural Gas Industries, Section 7.5 Piping and Appurtenances. Corrected during inspection.