Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 911293.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,380.00
Current Penalty: $1,428.00
Issuance Date: 11/26/2013
Nr Instances: 6
Nr Exposed: 1
Abatement Date: 01/10/2014
Gravity: 5
Report ID: 0627510
Contest Date:
Final Order: 12/11/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/11/2013 | $1,428.00 | 01/10/2014 | Serious | |
| Penalty | Z: Issued | 11/26/2013 | $2,380.00 | 12/09/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: On or about June 5, 2013, employees were exposed to unexpected start-up hazards in that the employer did not develop and implement energy control procedures including the following, but not limited to: a) 50 inch Hooper Press - Serial #WWSG2P911E. b) 50 inch Press Greene Line Stacker - Serial #1177A2. c) 50 inch Stanley Flexo - Serial #W6107. d) 50 inch Koopers Counter Ejector - Serial #1177A2. e) 35 inch Bostich Flexo - Serial #7879. f) 35 inch Flexo Printech Counter Ejector - Serial #128.