Violation Detail
Standard Cited: 19100036 G01 Design and construction requirements for exit routes.
Inspection Nr: 909304.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,100.00
Current Penalty: $1,050.00
Issuance Date: 07/23/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/06/2013
Gravity: 1
Report ID: 0111500
Contest Date:
Final Order: 08/16/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | $1,050.00 | 11/06/2013 | Serious | ||
| Penalty | I: Informal Settlement | 08/16/2013 | $1,050.00 | 10/07/2013 | Serious | |
| Penalty | Z: Issued | 07/23/2013 | $2,100.00 | 08/06/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.36(g)(1): Ceiling of an exit route was not at least seven feet six inches. Any projection from the ceiling must not reach a point less than six feet eight inches from the floor. Facility: The exit door indicated on the evacuation plan for egress from the paint booth area measured approximately 73 inches (6'1") from the concrete floor to the top of the door jam and the opening was reduced by an approximately 5 inch board at the bottom.
Translate