Violation Detail
Standard Cited: 19100107 E09 Spray finishing using flammable and combustible materials.
Inspection Nr: 881684.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 08/07/2013
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 08/13/2013
Gravity: 10
Report ID: 0524530
Contest Date:
Final Order: 09/04/2013
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 08/07/2013 | $7,000.00 | 08/13/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.107(e)(9): Flammable liquids for use in spraying operations were transferred from one container to another without both containers being effectively bonded and grounded to prevent discharge sparks of static electricity. a) On or about February 11, 2013, while working in the Paint Booth Building, an employee was exposed to explosion and fire hazards while cleaning the paint spray gun by spraying thinners and/or cleaners through the painting system into a metal barrel. The metal barrel was not bonded or electrically connected to the paint spray gun.