Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 843363.015
Citation: 01001
Citation Type: Serious
Abatement Date: 03/12/2013 2
Initial Penalty: $2,525.00
Current Penalty: $1,515.00
Issuance Date: 02/21/2013
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 1
Report ID: 0134000
Contest Date:
Final Order: 03/20/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/20/2013 | $1,515.00 | 03/12/2013 | Serious | |
Penalty | Z: Issued | 02/21/2013 | $2,525.00 | 03/12/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed. (a) Location - 626 Lynnway, Lynn, MA 01901: On or about 1/24/2013, the employer failed to ensure that written lock out tag out procedures were evaluated for effectiveness at least annually.