Violation Detail
Standard Cited: 19260652 C02 III Requirements for protective systems.
Inspection Nr: 551758.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $3,300.00
Current Penalty: $0.00
Issuance Date: 09/10/2012
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/01/2012
Gravity:
Report ID: 0521700
Contest Date:
Final Order: 09/28/2012
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/28/2012 | $0.00 | 10/01/2012 | Other | |
| Penalty | Z: Issued | 09/10/2012 | $3,300.00 | 10/01/2012 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.652(c)(2)(iii): Manufacturer's specifications, recommendations, and limitations, and manufacturer's approval to deviate from the specifications, recommendations, and limitations shall be in written form at the jobsite during construction of the protective system. After that time this data may be stored off the jobsite, but a copy shall be made available to the Secretary upon request. a. On or about July 23, 2012 - at the above addressed jobsite, the manufacturer's specifications, recommendations, and limitations, and manufacturer's approval to deviate from the specifications, recommendations, and limitations were not available in a written form at the jobsite during construction of the protective systems.
Translate