Violation Detail
Standard Cited: 19100119 J04 III Process safety management of highly hazardous chemicals.
Inspection Nr: 313880775
Citation: 01001
Citation Type: Serious
Abatement Date: 05/25/2011 X
Initial Penalty: $4,675.00
Current Penalty: $2,800.00
Issuance Date: 04/08/2011
Nr Instances: 2
Nr Exposed: 250
Related Event Code (REC):
Gravity: 05
Report ID: 0419700
Contest Date:
Final Order:
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/21/2011 | $2,800.00 | 05/25/2011 | Serious | |
Penalty | Z: Issued | 04/08/2011 | $4,675.00 | 05/25/2011 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard: CHEMNEP
29 CFR 1910.119(j)(4)(iii): The frequency of inspections and tests of process equipment to maintain its mechanical integrity, was not consistent with applicable manufacturers' recommendations and good engineering practices, or more frequently determined to be necessary by prior operating experience: a.On or about January 3, 2011, tests and inspection for the equipment contained in the refrigeration system, such as, but not limited to, Pressure Vessel (V35) were not completed with the normal frequencies established in the Preventive Maintenance program used by the company. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED.