Violation Detail
Standard Cited: 5A0001 OSH Act General Duty Paragraph
Inspection Nr: 310988712
Citation: 01001
Citation Type: Serious
Abatement Date: 08/04/2008 X
Initial Penalty: $5,000.00
Current Penalty: $5,000.00
Issuance Date: 07/25/2008
Nr Instances: 3
Nr Exposed: 5
Related Event Code (REC):
Gravity: 10
Report ID: 0418400
Contest Date: 07/25/2008
Final Order: 07/07/2010
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/07/2010 | $5,000.00 | 08/04/2008 | Serious | |
Penalty | Z: Issued | 07/25/2008 | $5,000.00 | 08/04/2008 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard: STRUCK BY
P.L. 91-596 Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer does not furnish employment and a place of employment which are free from recognized hazards that are causing or likely to cause death or serious physical harm to employees in that employees are exposed to the hazard(s) of being struck by falling equipment and/or materials: a.Bulk Sugar Building, 4th floor North wall - On or about 02/07/2008, employees operated a two-ton air operated hoist to lift materials and/or equipment that was not equipped with a throat latch to prevent detachment of the load and rigging from the hook, exposing employees to being struck-by a falling suspended load. b.Centrifugal area of Affination Station - On or about 02/07/2008, employees operated an electric hoist to lift materials and/or equipment that was not equipped with a throat latch to prevent the load and the rigging to prevent detachment of the load and rigging from the hook, exposing employees to being struck-by a falling suspended load. c.Motor Room - On or about 02/07/2008, employees operated a 2-ton C & M crane hoist to lift materials and/or equipment that was not equipped with a throat latch to prevent detachment of the load and rigging from the hook, exposing employees to being struck-by a falling suspended load. One feasible means of abatement would be to ensure that each of the hoist hooks used at the facility have throat latches, as referenced in ANSI B30.16-1973, Chapter 16-2 Electric Powered Hoists; section 16-2.1.2.10 d. Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days, the employer must submit an abatement plan describing the actions it is taking to prevent the hazards described in instances a through c, above.h