Violation Detail
Standard Cited: 19261402 B
Inspection Nr: 1867841.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,895.00
Current Penalty: $14,895.00
Issuance Date: 01/16/2026
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 01/23/2026
Gravity: 10
Report ID: 0213100
Contest Date: 01/22/2026
Final Order:
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 01/22/2026 | $14,895.00 | 01/23/2026 | Serious | |
| Penalty | Z: Issued | 01/16/2026 | $14,895.00 | 01/23/2026 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.1402(b): The equipment was assembled or used without ensuring that ground conditions are firm, drained, and graded to a sufficient extent so that, in conjunction (if necessary) with the use of supporting materials, the equipment manufacturer's specifications for adequate support and degree of level of the equipment are met: a) Worksite, mobile crane: On or about July 22, 2025, employees were assembling a Liebherr LTM 1220 mobile crane and the employer did not ensure that the ground conditions were graded to a sufficient extent.