Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1845076.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $16,550.00
Issuance Date: 01/30/2026
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 06/10/2026
Gravity: 10
Report ID: 0830500
Contest Date: 02/26/2026
Final Order: 04/10/2026
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 04/10/2026 | $16,550.00 | 06/10/2026 | Serious | |
| Penalty | C: Contested | 02/26/2026 | $16,550.00 | 02/26/2026 | Serious | |
| Penalty | Z: Issued | 01/30/2026 | $16,550.00 | 02/26/2026 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(d)(2)(iii): Procedures shall be developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: On or about August 18, 2025, the host employer failed to ensure that procedures for the control of hazardous energy were strictly adhered to. Technicians (both employees of the company and subcontracted employees) were not protected from hazards created by arc flash/arc blast in that technicians engaged in the group lockout of the PCS 025 (SG4400UD-MV-US, Serial #T2520600152) did not verify that electrical energy had been de-energized, and isolated, prior to commencing maintenance activities.