Violation Detail
Standard Cited: 19100179 N03 I Overhead and gantry cranes.
Inspection Nr: 1840784.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $16,550.00
Issuance Date: 01/23/2026
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 02/11/2026
Gravity: 10
Report ID: 0626600
Contest Date: 02/02/2026
Final Order:
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 02/02/2026 | $16,550.00 | 02/11/2026 | Serious | |
| Penalty | Z: Issued | 01/23/2026 | $16,550.00 | 02/11/2026 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.179(n)(3)(i): The load was not well secured and properly balanced in the sling or lifting device before it was lifted more than a few inches. On or about July 25, 2025, and at times prior, in the Metro Parts section of Toshiba International, the load was not properly secured and balanced when an employee was moving large metal rods from receiving to the storage cradles.
Translate