Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1813583.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,550.00
Current Penalty: $16,550.00
Issuance Date: 06/09/2025
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 07/07/2025
Gravity: 10
Report ID: 0521700
Contest Date:
Final Order: 07/10/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 06/09/2025 | $16,550.00 | 07/07/2025 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Production - On or about March 18, 2025, and days prior to, authorized employees were required to perform servicing and/or maintenance on the Morrill and Moeller ovens, Midwest Mixing mixers, Morrill and Moeller washers, Dayton exhaust fans, and other operating equipment. The employer did not ensure periodic inspections of the energy control procedures were performed at least annually as required by the standard.