Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1777865.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,276.00
Current Penalty: $8,276.00
Issuance Date: 03/24/2025
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/17/2025
Gravity: 5
Report ID: 0418800
Contest Date: 04/17/2025
Final Order:
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 04/18/2025 | $8,276.00 | 04/17/2025 | Serious | |
Penalty | Z: Issued | 03/24/2025 | $8,276.00 | 04/17/2025 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): On or about September 25, 2024, on the east side of the construction site located at 4465 Griffin Rd, Davie, Florida 33314, an employee was exposed to a 12-foot fall hazard while working from a tubular welded frame scaffold that was not fully planked.