Violation Detail
Standard Cited: 19260451 F06 General requirements.
Inspection Nr: 1769782.015
Citation: 01001
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $6,452.00
Current Penalty: $3,226.00
Issuance Date: 11/12/2024
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 10
Report ID: 0214500
Contest Date:
Final Order: 12/12/2024
Related Event Code (REC): I
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/12/2024 | $3,226.00 | Serious | ||
| Penalty | Z: Issued | 11/12/2024 | $6,452.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(f)(6):Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6). a) At or near 628 Market St, Paterson NJ - Pump Jack Scaffold - E 23rd St Facade: employee was exposed to electric hazards while installing vent caps utilizing a pump jack scaffold platform supported by aluminum poles that were approximately 7 feet from a 4KV energized primary line, on or about 8/19/24