Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1766730.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $12,098.00
Issuance Date: 01/02/2025
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 03/03/2025
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 01/28/2025
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/28/2025 | $12,098.00 | 03/03/2025 | Other | |
Penalty | Z: Issued | 01/02/2025 | $16,131.00 | 01/10/2025 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy. On or about July 28,2024, the employer did not provide a clear energy control procedure for shutting down, isolating, blocking and securing the 86-3 winder machine to control hazardous energy.