Violation Detail
Standard Cited: 19100212 A03 II General requirements for all machines.
Inspection Nr: 1742553.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $11,291.70
Issuance Date: 06/11/2024
Nr Instances: 2
Nr Exposed: 10
Abatement Date: 07/01/2024
Gravity: 10
Report ID: 0521700
Contest Date:
Final Order: 07/01/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/01/2024 | $11,291.70 | 07/01/2024 | Serious | |
| Penalty | Z: Issued | 06/11/2024 | $16,131.00 | 07/01/2024 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.212(a)(3)(ii): Point of operation guards were not designed and constructed as to prevent the operator from having any part of their body in the danger zone during the operating cycle: a. On or about April 19, 2024, in the production area, employees were required to operate the GED Saws Machine No. 20056 on a daily basis. The employer failed to ensure fingerguards guards were adjusted on the saw to prevent the operator from having any parts of their body in the danger zone during the cutting process. Employees were thereby exposed to the hazards associated with unguarded points of operation during the operating cycles. b. On or about April 19, 2024, in the production area, employees were required to operate the Pneumatic Punch Presses on a daily basis. The employer failed to provide adequately design and construct guards for the equipment to prevent the operator from having any parts of their body in the danger zone. Employees were thereby exposed to the hazards associated with unguarded points of operation during the operating cycles.