Violation Detail
Standard Cited: 19100303 B07 III General.
Inspection Nr: 1714405.015
Citation: 01001
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $11,524.00
Current Penalty: $3,500.00
Issuance Date: 05/30/2024
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0111400
Contest Date: 06/26/2024
Final Order: 10/15/2024
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/15/2024 | $3,500.00 | Other | ||
Penalty | C: Contested | 06/27/2024 | $11,524.00 | Serious | ||
Penalty | Z: Issued | 05/30/2024 | $11,524.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.303(b)(7)(iii): Internal parts of electrical equipment, including busbars, wiring terminals, insulators, and other surfaces, were damaged or contaminated by foreign materials such as paint, plaster, cleaners, abrasives, or corrosive residues: Bagging Area: A 480-volt electrical circuit panel that energized the bagging equipment such as the robot machine and conveyor belt motors was not effectively closed and allowed infiltration of concrete dust.