Violation Detail
Standard Cited: 19100268 B07 Telecommunications.
This violation item has been deleted.
Inspection Nr: 1653834.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $4,688.00
Current Penalty: $0.00
Issuance Date: 08/21/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 09/15/2023
Gravity: 10
Report ID: 0213900
Contest Date: 09/21/2023
Final Order: 12/11/2023
Related Event Code (REC): A;R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 12/11/2023 | $0.00 | 09/15/2023 | Serious | |
| Penalty | C: Contested | 09/26/2023 | $4,688.00 | 09/15/2023 | Serious | |
| Penalty | Z: Issued | 08/21/2023 | $4,688.00 | 09/15/2023 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.268(b)(7):The employer did not ensure that no employee approached or took any conductive object closer to any electrically energized overhead power lines and parts as prescribed in Table R-2 or in (i) - (iii) of this section: a) 11 South Gold Drive, Hamilton, NJ - Rear parking lot - The employer did not ensure that the employee working for the company maintained approach distance of at least 24 inches from uninsulated energized (13.2kV) overhead powerlines, thus exposing the employee to electrocution hazards. An employee working from an aerial lift on top of a box truck was fatally injured after coming in contact with energized power lines. Noted on or about March 1, 2023. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.