Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1627298.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,360.00
Current Penalty: $6,000.00
Issuance Date: 12/30/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/31/2023
Gravity: 5
Report ID: 0521400
Contest Date:
Final Order: 01/25/2023
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/25/2023 | $6,000.00 | 01/31/2023 | Serious | |
| Penalty | Z: Issued | 12/30/2022 | $10,360.00 | 01/31/2023 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
1910.147(c)(6)(ii) The employer shall certify that the periodic inspections have been performed. The certification shall identify the machine or equipment on which the energy control procedure was being utilized, the date of the inspection, the employees included in the inspection, and the person performing the inspection. On or about September 23, 2022, the employer did not certify that a periodic inspection was conducted on the energy control procedure for Crossover Conveyor #2. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).