Standard Cited: 19100269 N02 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1577337.015
Citation: 01001
Citation Type: Other
Abatement Date: 01/03/2024 5
Initial Penalty: $14,502.00
Current Penalty: $14,502.00
Issuance Date: 07/01/2022
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date: 07/12/2022
Final Order: 11/03/2023
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 11/03/2023 | $14,502.00 | 01/03/2024 | Other | |
Penalty | C: Contested | 07/18/2022 | $14,502.00 | 07/28/2022 | Serious | |
Penalty | Z: Issued | 07/01/2022 | $14,502.00 | 07/28/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(n)(2): For any employee to work transmission and distribution lines or equipment as deenergized, the employer did not ensure that the lines or equipment were deenergized under the provisions of paragraph (m) of this section and did not ensure proper grounding of the lines or equipment as specified in paragraphs (n)(3) through (n)(8) of this section: (a) On or about February 4, 2022 at the site employees were exposed to electrocution hazards when attempting to repair transmission lines while energized.