Violation Detail
Standard Cited: 19100147 C04 II D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1570855.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,287.00
Current Penalty: $6,215.00
Issuance Date: 03/15/2022
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/15/2022
Gravity: 5
Report ID: 0523300
Contest Date:
Final Order: 04/07/2022
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/07/2022 | $6,215.00 | 04/15/2022 | Serious | |
| Penalty | Z: Issued | 03/15/2022 | $8,287.00 | 03/29/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(D): The energy control procedures did not clearly and specifically outline the requirements for testing a machine or equipment to determine and verify the effectiveness of lockout devices, tagout devices, and other energy control measures. On or about December 27, 2021, at the previously addressed job site, the energy control procedure for the thermorformer did not clearly and specifically outline the requirements for testing the machine to determine and verify the effectiveness of the pin and lock devices controlling the ovens gravity energy sources. Abatement certification is required for this item in accordance with the requirements of 29 CFR 1903.19(c).