Violation Detail
Standard Cited: 19260451 C02 V General requirements.
Inspection Nr: 1568104.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,801.00
Current Penalty: $4,350.75
Issuance Date: 03/18/2022
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/06/2022
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 04/07/2022
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection | 
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/07/2022 | $4,350.75 | 04/06/2022 | Serious | |
| Penalty | Z: Issued | 03/18/2022 | $5,801.00 | 04/06/2022 | Serious | 
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(c)(2)(v): The employer used forklifts to support scaffold platforms without ensuring that the entire platform was attached to the fork and that the forklift was not moved horizontally while the platform was occupied: (a) Dixey Land Energy at Customer Warehouse 902 Strasburg Pike Strasburg PA - The employer allowed an employee on an elevated surfaces of a wooden skid that was not attached/secured to the forklift, on or about December 10, 2021. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.