Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 1563783.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $9,324.00
Current Penalty: $5,594.40
Issuance Date: 01/20/2022
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): R
Gravity: 5
Report ID: 0636900
Contest Date:
Final Order: 02/10/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/10/2022 | $5,594.40 | Serious | ||
Penalty | Z: Issued | 01/20/2022 | $9,324.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.219(c)(4)(i): Projecting shaft ends did not present a smooth edge and end and projected more than one-half the diameter of the shaft without being guarded by nonrotating caps or safety sleeves. On or about November 5, 2021, and at times prior thereto, the employer did not ensure that the projecting shaft end of the hammer mill was protected or guarded to prevent employees from being caught-in or struck-by the rotating shaft.