Violation Detail
Standard Cited: 19100269 C01 II Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1543984.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $13,653.00
Current Penalty: $0.00
Issuance Date: 11/17/2021
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 01/06/2022
Gravity: 10
Report ID: 0524530
Contest Date: 12/13/2021
Final Order: 04/19/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/19/2023 | $0.00 | 01/06/2022 | Serious | |
Penalty | C: Contested | 12/14/2021 | $13,653.00 | 01/06/2022 | Serious | |
Penalty | Z: Issued | 11/17/2021 | $13,653.00 | 01/06/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(c)(1)(ii): The employer did not ensure that the employee in charge conducted a job briefing that met paragraphs (c)(2) though (c)(4) of this section with the employees involved before they start each job. On or about July 23, 2021, a job briefing was not conducted to discuss energy-source controls, and replacement of a 12 kV recloser between two crews working inside of a substation.