Violation Detail
Standard Cited: 19260403 E General requirements.
Inspection Nr: 1542473.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,973.00
Current Penalty: $2,983.80
Issuance Date: 09/07/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 09/21/2021
Gravity: 1
Report ID: 0523900
Contest Date:
Final Order: 09/16/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/16/2021 | $2,983.80 | 09/21/2021 | Serious | |
| Penalty | Z: Issued | 09/07/2021 | $4,973.00 | 09/21/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.403(e): All splices and joints and free ends of conductors were not covered with insulation equivalent to that of the conductors or with an insulating device designed for the purpose: (a) At the back of the construction site job trailer: The spliced ends of the conductors were covered with electrical tape and did not have insulation properties that were equivalent to the wires being connected.