Standard Cited: 19100219 C02 I Mechanical power-transmission apparatus.
Inspection Nr: 1525350.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,655.00
Current Penalty: $6,275.75
Issuance Date: 05/05/2021
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/04/2021
Gravity: 5
Report ID: 0418100
Contest Date:
Final Order: 06/01/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/01/2021 | $6,275.75 | 06/04/2021 | Serious | |
| Penalty | Z: Issued | 05/05/2021 | $9,655.00 | 05/24/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.219(c)(2)(i):All exposed part(s) of horizontal shafting seven (7) feet or less from floor or working platform were not protected by stationary casing(s) enclosing shafting completely or by trough(s) enclosing sides and top or sides and bottom of shafting: On or about 4/14/2021 workers were exposed to amputation hazards due to unguarded horizontal shafts at the top line, right, left, and below the conveyor of the tail pulley.