Violation Detail
Standard Cited: 19100269 A03 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1507500.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $13,653.00
Current Penalty: $13,653.00
Issuance Date: 05/28/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/14/2022
Gravity: 10
Report ID: 0626300
Contest Date: 06/25/2021
Final Order: 04/14/2022
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/14/2022 | $13,653.00 | 06/14/2022 | Other | |
Penalty | C: Contested | 07/09/2021 | $13,653.00 | 06/24/2021 | Serious | |
Penalty | Z: Issued | 05/28/2021 | $13,653.00 | 06/24/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(a)(3)(iii):The contract employer and the host employer did not coordinate their work rules and procedures so that each employee of the contract employer and the host employer was protected as required by this section: (a) On or about December 19, 2020, an employee inspecting electrical equipment was exposed to an electrical hazard when the employer did not coordinate their work rules and procedures with the host employer.