Violation Detail
Standard Cited: 19100303 B07 I General.
Inspection Nr: 1505554.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,728.00
Current Penalty: $1,000.00
Issuance Date: 06/02/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/14/2021
Gravity: 5
Report ID: 0316700
Contest Date: 06/28/2021
Final Order: 09/17/2023
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/17/2023 | $1,000.00 | 06/14/2021 | Serious | |
Penalty | C: Contested | 06/30/2021 | $10,728.00 | 06/14/2021 | Serious | |
Penalty | Z: Issued | 06/02/2021 | $10,728.00 | 06/14/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.303(b)(7)(i):Unused openings in boxes, raceways, auxiliary gutters, cabinets, equipment cases, or housings were not effectively closed to afford protection substantially equivalent to the wall of the equipment. a) Stock room - The employer did not ensure that the electrical panel marked "RP" 100 AMP had the required blank covers installed for breakers that were missing inside the box, therefore, exposing employees to shock hazards on or about December 9, 2021. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.