Standard Cited: 19100269 N02 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1480697.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,446.00
Current Penalty: $4,723.00
Issuance Date: 12/07/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/04/2021
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 01/15/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/15/2021 | $4,723.00 | 01/04/2021 | Serious | |
| Penalty | Z: Issued | 12/07/2020 | $9,446.00 | 01/04/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(o)(3)(ii)[C]: For employees working transmission and distribution lines or equipment as deenergized, the employer did not ensure that the lines or equipment were deenergized under the provisions of paragraph (m) of this section and did not ensure proper grounding of the lines or equipment as specified in paragraphs (n)(3) through (n)(8) of this section: a) On or about June 23, 2020, at Power Station 3, 35 Gen substation of Motiva refinery, all breakers and switches were not grounded when employees were working on them as deenergized.