Violation Detail
Standard Cited: 19100217 F02 Mechanical power presses.
Inspection Nr: 1466339.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,446.00
Current Penalty: $6,000.00
Issuance Date: 05/29/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 06/26/2020
Gravity: 10
Report ID: 0521400
Contest Date:
Final Order: 06/25/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/25/2020 | $6,000.00 | 06/26/2020 | Serious | |
Penalty | Z: Issued | 05/29/2020 | $9,446.00 | 06/26/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
Operator(s) were not trained and instructed in the safe method of work before starting work on mechanical power press(es). The employer did not insure by adequate supervision that correct operating procedures were being followed. On or about February 19, 2020 an employee was assigned to work on a punch press and was not adequately trained and supervised on how to run the machine safely. The employee was exposed to amputation hazards while operating the punch press. Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).