Standard Cited: 19260405 G02 III Wiring methods, components, and equipment for general use.
Inspection Nr: 1464462.015
Citation: 01001
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $2,545.00
Current Penalty: $2,545.00
Issuance Date: 03/05/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 03/30/2020
Gravity: 1
Report ID: 0524700
Contest Date:
Final Order: 03/31/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/05/2020 | $2,545.00 | 03/30/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.405(g)(2)(iii): The repair splice in a hard service flexible cord No. 12 or larger did not retain the insulation, outer sheath properties, and usage characteristics of the cord which was being used: (a) Blue Chip Construction LLC / Blue Chip Housing LLC, on or about February 21st, 2020, at the location of 827 Weadock Ave., Lima, OH, 45804: The employer did not ensure that employees were protected from shock hazards while using an extension cord that had been damaged and inappropriately repaired so as not to retain its protective properties. The extension cord was used to power an air compressor and a portable circular saw alternatively.