Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1458214.015
Citation: 01001
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $4,048.00
Current Penalty: $1,124.00
Issuance Date: 07/20/2020
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 10
Report ID: 0214700
Contest Date: 09/23/2020
Final Order: 03/18/2021
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 03/18/2021 | $1,124.00 | Serious | ||
Penalty | C: Contested | 09/23/2020 | $4,048.00 | Serious | ||
Penalty | Z: Issued | 07/20/2020 | $4,048.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights. a) Worksite, 57 Glenmore Ave, Montauk NY, West Side of Building - Employees were performing cedar shake siding installation work from a 4-tier fabricated frame scaffold approximately 20-feet above the ground that was not fully planked, on or about 01/24/2020. Note: Because abatement of this violation is already documented in the case file, the employer need not submit certification or documentation of abatement for this violation as normally required by CFR 1903.19.