Violation Detail
Standard Cited: 19260451 F07 General requirements.
Inspection Nr: 1450085.015
Citation: 01001
Citation Type: Serious
Abatement Date: 03/20/2020 2
Initial Penalty: $9,639.00
Current Penalty: $4,819.50
Issuance Date: 02/18/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 5
Report ID: 0112600
Contest Date:
Final Order: 03/09/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/09/2020 | $4,819.50 | 03/20/2020 | Serious | |
Penalty | Z: Issued | 02/18/2020 | $9,639.00 | 03/20/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(f)(7): Scaffolds had not been erected, moved, dismantled or altered only under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling, or alteration. 34 Spring Street, Williamstown, MA : On or about December 10, 2019 two employees were working with a Genie AWP-40S mobile elevated work platform (scaffold) and it had not been erected or dismantled under the supervision of a competent person to ensure that stabilizer pads were not adjusted or lowered at any times the platform was elevated or occupied. Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).