Violation Detail
Standard Cited: 19260651 B04 Specific Excavation Requirements.
Inspection Nr: 1446227.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,205.00
Current Penalty: $13,494.00
Issuance Date: 04/27/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 05/21/2020
Gravity: 1
Report ID: 0830400
Contest Date:
Final Order: 05/21/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/21/2020 | $13,494.00 | 05/21/2020 | Serious | |
Penalty | Z: Issued | 04/27/2020 | $5,205.00 | 05/21/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.651(b)(4): While the excavation was opened, underground installations were not protected, supported or removed as necessary to safeguard employees: (a)Krohmer Plumbing, Inc. at Vincent Place & South Miller Avenue, Mitchell, SD 57301: On or about and at times prior to November 20, 2019, the employer did not ensure that a gas main within the excavation was protected, supported or removed while employees were performing work within the excavation.