Violation Detail
Standard Cited: 19260451 C02 I General requirements.
Inspection Nr: 1437092.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,858.00
Current Penalty: $4,858.00
Issuance Date: 01/23/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 02/26/2020
Gravity: 10
Report ID: 0420300
Contest Date:
Final Order: 01/24/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/24/2020 | $4,858.00 | 02/26/2020 | Serious | |
| Penalty | Z: Issued | 01/23/2020 | $4,858.00 | 02/26/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(c)(2)(i): Footings were not level, sound, rigid, and capable of supporting the loaded scaffold without settling or displacement: On or before October 7, 2019, Hydro Mobile M2 series mast climbing work platforms (MCWPs) were not set on a firm foundation with substantial mud sills capable of supporting the loads imposed. Employees were exposed to fall hazards of approximately 35 feet.