Violation Detail
Standard Cited: 19100147 D02 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1425763.015
Citation: 01001
Citation Type: Serious
Abatement Date: 12/20/2019 2
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 10/30/2019
Nr Instances: 1
Nr Exposed: 9
Related Event Code (REC): R
Gravity: 10
Report ID: 0522500
Contest Date:
Final Order: 11/26/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/26/2019 | $13,260.00 | 12/20/2019 | Serious | |
Penalty | Z: Issued | 10/30/2019 | $13,260.00 | 12/04/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(d)(2): Machine or equipment shutdown. The machine or equipment shall be turned off or shut down using the procedures established for the machine or equipment. An orderly shutdown must be utilized to avoid any additional or increased hazard(s) to employees as a result of the equipment stoppage. a. On or about August 6 2019, the employer did not require maintenance employees to deenergize and lockout the Slider Frame Welder Machine during servicing and maintenance activities, which led to an amputation injury.