Violation Detail
Standard Cited: 19260350 A07 Gas welding and cutting.
Inspection Nr: 1422999.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/13/2020
Nr Instances: 1
Nr Exposed: 9
Abatement Date: 03/11/2020
Gravity:
Report ID: 0336000
Contest Date:
Final Order: 03/12/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 02/13/2020 | $0.00 | 03/11/2020 | Other |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.350(a)(7): A suitable cylinder truck, chain, or other steadying device was not used to keep compressed gas cylinder(s) from being knocked over: a.) Iseler Demolition, Inc./Water Tank Demolition Project/ 4451 New Castle Road, New Wilmington, PA: On or about August 13, 2019, the fuel gas cylinders (i.e. flammable gas cylinders/tanks) utilized for cutting work on the water tank were not secured from being knocked over.
Translate