Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1422982.015
Citation: 01001
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $3,978.00
Current Penalty: $2,502.00
Issuance Date: 01/02/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 10
Report ID: 0213400
Contest Date: 11/12/2020
Final Order: 05/17/2021
Related Event Code (REC): C;I
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 05/17/2021 | $2,502.00 | Serious | ||
| Penalty | C: Contested | 02/17/2021 | $3,978.00 | Serious | ||
| Penalty | Z: Issued | 01/02/2020 | $3,978.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii). A) 1300 Livingston Ave, North Brunswick, NJ: Scaffold that was in use was not fully planked on all working levels of the scaffold. Condition observed on or about 05JUL19