Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1416695.015
Citation: 01001
Citation Type: Serious
Abatement Date: 01/03/2020
Initial Penalty: $11,934.00
Current Penalty: $0.00
Issuance Date: 12/20/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0625700
Contest Date: 01/16/2020
Final Order: 09/22/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/22/2021 | $0.00 | 01/03/2020 | Serious | |
Penalty | C: Contested | 02/25/2020 | $11,934.00 | 01/03/2020 | Serious | |
Penalty | Z: Issued | 12/20/2019 | $11,934.00 | 01/03/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: On or about June 26, 2019, front of building-west side, the employer did not have steps in the written energy control procedures for isolating the electrical and pneumatic energy sources on the Atlas Copco BD-850 air dryer.