Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1402161.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $5,115.00
Current Penalty: $5,115.00
Issuance Date: 06/13/2019
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 07/10/2019
Gravity:
Report ID: 0214500
Contest Date:
Final Order: 07/10/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/10/2019 | $5,115.00 | 07/10/2019 | Other | |
| Penalty | Z: Issued | 06/13/2019 | $5,115.00 | 07/10/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Plant-Wide: Employees are required to conduct lockout/tagout procedures prior to performing servicing and/or repair on machines and equipment, including but not limited to, Orni A & B washing machines, and the flipper machine. The employer did not conduct annual periodic inspection for authorized employees, on or about 5/20/19.