Standard Cited: 19260451 F07 General requirements.
Inspection Nr: 1400284.015
Citation: 01001
Citation Type: Other
Abatement Date: 3
Initial Penalty: $9,282.00
Current Penalty: $9,282.00
Issuance Date: 10/09/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0626700
Contest Date: 11/06/2019
Final Order: 05/19/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/19/2021 | $9,282.00 | Other | ||
Penalty | C: Contested | 11/14/2019 | $9,282.00 | Serious | ||
Penalty | Z: Issued | 10/09/2019 | $9,282.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration: a) At Tank 150-4, wind girder plate scaffold was not dismantled under the direction and supervision of a competent person. Employees working on the scaffold, approximately 56 feet above the paved ground, were exposed to fall hazards.