Violation Detail
Standard Cited: 19100119 D03 I D Process safety management of highly hazardous chemicals.
Inspection Nr: 1381782.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,741.00
Current Penalty: $6,444.60
Issuance Date: 07/25/2019
Nr Instances: 3
Nr Exposed: 7
Abatement Date: 11/07/2019
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 08/09/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | $6,444.60 | 11/07/2019 | Serious | ||
Penalty | I: Informal Settlement | 08/09/2019 | $6,444.60 | 11/07/2019 | Serious | |
Penalty | Z: Issued | 07/25/2019 | $10,741.00 | 08/13/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.119(d)(3)(i)(D): Information pertaining to the equipment in the process did not include relief system design and design basis: The violation occurred at the Chemicals, Inc. facility located in Baytown, TX on February 28, 2018 when the employer failed to ensure process safety information includes the pressure relief design and design basis, such as but not limited to: 1. Conventional relief valve made by Ferris (S/N F-01117-778-1) for TK-708 Methanol tank 2. Conventional relief valve manufactured by Lonergan (S/N 880573-14-1) for RX-F7 reactor 3. Pressure relief device Lonegran (S/N H-86-791, model D10 J/S4/SP) for RX-F15 reactor