Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1378859.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,525.00
Current Penalty: $5,115.00
Issuance Date: 04/24/2019
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 05/07/2019
Gravity: 5
Report ID: 0524700
Contest Date:
Final Order: 05/16/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/16/2019 | $5,115.00 | 05/07/2019 | Serious | |
| Penalty | Z: Issued | 04/24/2019 | $8,525.00 | 05/07/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed: a. On or February 14, 2019, a periodic inspection of the energy control procedures was not performed to ensure that lockout/tagout procedure and requirements of 29 CFR 1910.147 were being followed. The employer did not assure that the energy control procedure for the TD-95 router was inspected.