Violation Detail
Standard Cited: 19260025 A Housekeeping.
Inspection Nr: 1369147.015
Citation: 01001
Citation Type: Serious
Abatement Date: 05/23/2019 2
Initial Penalty: $2,273.00
Current Penalty: $1,200.00
Issuance Date: 05/17/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0316100
Contest Date:
Final Order: 06/10/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/10/2019 | $1,200.00 | 05/23/2019 | Serious | |
Penalty | Z: Issued | 05/17/2019 | $2,273.00 | 05/23/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.25(a): During the course of construction, alteration, or repairs, debris was not kept cleared from work areas, passageways, and stairs, in and around buildings or other structures: Front Entrance and Right Side of Structure - Workers had to climb over building materials scrap lumber, trash and debris that was thrown randomly throughout the area preventing a clear passage to the structure and work areas, on or about 1/3/19. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).