Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1363763.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,472.00
Current Penalty: $5,683.20
Issuance Date: 01/23/2019
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 02/19/2019
Gravity: 5
Report ID: 0627510
Contest Date:
Final Order: 02/07/2019
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/07/2019 | $5,683.20 | 02/19/2019 | Serious | |
| Penalty | Z: Issued | 01/23/2019 | $9,472.00 | 02/19/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): On or about November 30, 2018 at the mill unit #4 sifter B, employees performed routine cleaning/maintenance on a Great Western HS Sifter without utilizing all of the isolating devices needed to isolate the machine from its energy sources.