Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1362654.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $10,210.00
Current Penalty: $7,000.00
Issuance Date: 02/28/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): I
Gravity: 10
Report ID: 0213400
Contest Date:
Final Order: 03/26/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/26/2019 | $7,000.00 | Serious | ||
Penalty | Z: Issued | 02/28/2019 | $10,210.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): a. 88 Claremont Rd., Bernardsville, NJ The employer did not ensure that the working level of a four tier tubular welded frame scaffold was fully planked. An employee engaged in masonry activities was working from a working level that had only two planks for landing materials. Violation observed on or about November 28, 2018