Violation Detail
Standard Cited: 19100176 A Handling materials - general.
Inspection Nr: 1341297.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $6,000.00
Issuance Date: 10/17/2018
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 11/15/2018
Gravity:
Report ID: 0627100
Contest Date:
Final Order: 11/08/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/08/2018 | $6,000.00 | 11/15/2018 | Other | |
| Penalty | Z: Issued | 10/17/2018 | $12,934.00 | 11/15/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.176(a): Where mechanical handling equipment was used, sufficient safe clearances were not allowed for aisles, a loading docks, through doorways and wherever turns of passage must be made: On or about August 14, 2018 and times prior thereto, in the Large Diameter Coating Area Final Table, employees required to stencil pipe information on finished pipes were not protected from rolling pipes from the jeeping station. This condition exposes employees to struck-by hazards.