Standard Cited: 19100269 O06 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1321293.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,467.00
Current Penalty: $5,000.00
Issuance Date: 10/02/2018
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/25/2018
Gravity: 5
Report ID: 0521400
Contest Date:
Final Order: 10/26/2018
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/26/2018 | $5,000.00 | 10/25/2018 | Serious | |
| Penalty | Z: Issued | 10/02/2018 | $6,467.00 | 10/25/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(o)(6)(ii): The test operator in charge shall conduct routine safety checks before each series of tests and shall verify the conditions: Albany Substation - On or about 04 June 2018, the employer did not ensure that an adequate safety check was conducted to ensure that an employee exposed to contact with 10,000 Volts (10kV) during power factor testing on a substation transformer, was required to use personal protective equipment, including voltage-rated rubber insulating gloves. An employee was exposed to shock/electrocution. Abatement documentation is required for this item in accordance with 29 CFR 1903.19(d).